Permitting
If your rack is taller than 12 feet, you almost certainly need a high-piled storage permit. The cheapest way to get one is to start before the rack ships. We handle the whole process and know the local rules.
Do You Need a High-Piled Storage Permit?
Under the International Fire Code, you need a permit once a building holds more than 500 square feet of high-piled combustible storage. “High-piled” means the top of the storage sits above 12 feet, or combustible materials sit in closely packed piles. “Combustible” counts the carton and the wood pallet, not just the product inside.
That covers most pallet rack projects. These are the common triggers we see.
- Storage with the top of the load above 12 feet, whether rack, shelving, or floor-stacked piles
- More than 500 square feet of high-piled storage area
- Combustible commodities, including Group A plastics in the product or its packaging
- A new tenant or a change of use in an existing building. New usage must meet current codes, even if the last occupant never needed to.
The order matters most. If you install the rack first and permit it second, you may be told to tear the system down and start over. Get the walkthrough before the anchors go in. Someone who knows the local rules can tell you what the building needs while changes are still cheap.
How Our Permitting Process Works
Site Walkthrough
Our team visits the jobsite to review warehouse conditions. We check sprinklers, emergency lighting, signage, and building conditions. We also compare the proposed layout against the actual facility conditions.
Schedule the Review Date
Once the project details are ready, we request a permit review date. These reviews are often scheduled three to four weeks out, so it’s important to start early. That timeline continues whether your rack materials have shipped or not.
Assemble the Permit Package
Engineers, along with an architect or CAD designer, prepare the sealed drawings for the permit package. We review them with you before submittal. Sometimes the building itself needs work first, such as adding an exit door or stairway, emergency lighting, or exit signs.
Permit Review & Pickup
We submit the application and sealed drawings before the review date. The reviewer checks the package and may ask for clarification. Once approved, we pick up the permit and send the stamped drawings to the job site before construction begins.
Inspections & Certificate of Occupancy
After installation, we request the required building and fire inspections. Electrical inspections may also be needed. Once the project passes inspection, you can receive the Certificate of Occupancy and begin operations.
Start to finish, plan on a couple of weeks to a few months depending on the jurisdiction. A month or more is common. Run the permit at the same time as your rack order, and most of that wait overlaps the factory lead time instead of adding to it.
What We Need to Start
To begin the permitting process we need a handful of details about the building and what is going in it. If you do not have drawings, that is not a problem.
- Building address
- Proposed rack layout
- Storage height
- Product type
- Pallet load information
- Any available building drawings
If drawings are not available, we can walk the site and gather the measurements ourselves.
What Goes in the Application
Requirements vary by county, but the core package is similar everywhere. If you can put this list together, you can permit almost anywhere. Two groups must sign off before the permit is issued: the Building Department and the Fire Department. Once the construction cost passes a certain amount, a licensed general contractor must run the project. Stein is a licensed GC.
- Permit application
- Building Code Summary (Appendix B) filled out for your facility and system
- List of commodities and how they are stored
- Sprinkler drawings and hydraulic design criteria
- PE-stamped structural drawings showing anchors, with details and calculations
- Seismic calculations
- Egress/floor plans showing rack layout, exits, and directional signage
To see what reviewers expect, here are examples of designs and drawings from our past projects, plus the fire code chapter that covers high-piled storage.
Permitting Anywhere We Work
Most Places Start From the Same Fire Code
Most jurisdictions work from the same fire code foundation, but adopted code editions, local amendments, paperwork requirements, and inspector interpretation can vary. The core triggers are consistent: the 12-foot and 500-square-foot thresholds, and the commodity classes (Class I through IV, high hazard, and Group A/B/C plastics) that set your sprinkler requirements. Wire decking is another helpful constant, since it usually lets rack be treated as rack without solid shelves, so sprinklers reach every level through the mesh and in-rack sprinklers can often be avoided.
The Paperwork Varies by County
Some counties want only the application, structural drawings, and seismic calculations. Stricter ones also require sealed electrical plans, lighted exit signs visible from every aisle with battery or generator backup, and emergency lighting that gives 1 FC at the floor.
The Inspector Varies Too
In our experience, rules get read inspector by inspector. What one approves, another may send back for changes in the same city. We cannot promise you an easy reviewer. We can put together drawings that leave little to argue with.
A package built for a strict county usually travels well, since the code backbone is shared. Local amendments and forms still differ, which is what we check before anything is submitted. Get the Permitting Guide
How a Rack Permit Comes Together
The rack layout is drawn and dimensioned, the seismic base detail is added, and the drawing is stamped and approved.
Permitting Questions
Do I need a permit for my pallet rack?
What happens if I install before getting a permit?
How long does the permitting process take?
What do I need to apply?
Can I get a permit for used pallet rack?
Does my seismic zone matter?
Who pulls the permit?